Eskom confirms Stage 4 loadshedding due to multiple unit trips at Camden Power Station, continuing until further notice.
South Africa got some slight relief on Monday after Eskom announced the end of stage 6 load shedding, lowering the level to ...
Eskom has downgraded load shedding to Stage 4 until further notice. The utility says it has managed to return eight out of 10 ...
Eskom has reduced load shedding to stage 4 until further notice due to the recovery of units at three power stations. This ...
“Although SA has been making progress regarding load shedding, the system remains at risk. This is because we do not have ...
The country was hit with stage 6 on Sunday morning following the failure of multiple units at some of Eskom's power stations.
Eskom CEO Dan Marokane says the country should be out of loadshedding by the end of the week. It’s after stage 6 ...
State-owned enterprise Eskom announced that the country would experience Stage 6 loadshedding after multiple units at three ...
While addressing the media in Pretoria on Sunday, Eskom CEO Dan Marokane stated that recovery plans were well underway, with ...
The electricity utility lost 10 generating units at the weekend but has said it is making good progress in restoring them to ...
South Africa's Eskom has restored six power units following significant power cuts due to failures at Majuba and Camden ...
Eskom announces Stage 3 load shedding after 20 days of uninterrupted power supply, citing a temporary setback.